Lavaca Bay Solar is a 243.5 MW solar interconnection project in Matagorda, Texas with a current status of active. It is proposed to connect at tap 345 kV REFUGE 42400 - JONES CREEK 47532 ckt 27.

243.5 MWCapacity
ActiveStatus
ERCOTMarket
SolarTechnology

Project facts

Canonical nameLavaca Bay Solar
Queue ID23INR0084
Statusactive
Source statusactive
MarketERCOT
TechnologySolar
Capacity243.5 MW
StateTexas
CountyMatagorda
Point of interconnectiontap 345 kV REFUGE 42400 - JONES CREEK 47532 ckt 27
Requested (queue) date2020-09-11
Proposed in-service date2026-12-31
Operational date
Withdrawn date
DeveloperLavaca Bay Solar Project, LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.