Line side tap using three breaker ring bus on 230kV Feeder from Gerald Gentleman to North Platte (GEN-2021-105)
Line side tap using three breaker ring bus on 230kV Feeder from Gerald Gentleman to North Platte is a 200.0 MW solar interconnection project in Lincoln, Nebraska with a current status of withdrawn. It is proposed to connect at Line side tap using three breaker ring bus on 230kV Feeder from Gerald Gentleman to North Platte.
Project facts
| Canonical name | Line side tap using three breaker ring bus on 230kV Feeder from Gerald Gentleman to North Platte |
|---|---|
| Queue ID | GEN-2021-105 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | NE |
| Technology | Solar |
| Capacity | 200.0 MW |
| State | Nebraska |
| County | Lincoln |
| Point of interconnection | Line side tap using three breaker ring bus on 230kV Feeder from Gerald Gentleman to North Platte |
| Requested (queue) date | 2021-05-26 |
| Proposed in-service date | 2027-10-19 |
| Operational date | — |
| Withdrawn date | 2023-07-14 |
| Developer | — |
| Utility / transmission owner | NPPD |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | withdrawn | high |
Explore related data
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.