Newport 69kV (W1-089)
Newport 69kV is a 18.0 MW solar interconnection project in Cumberland, New Jersey with a current status of withdrawn.
18.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology
Project facts
| Canonical name | Newport 69kV |
|---|---|
| Queue ID | W1-089 |
| Status | withdrawn |
| Source status | Withdrawn |
| Market | — |
| Technology | Solar |
| Capacity | 18.0 MW |
| State | New Jersey |
| County | Cumberland |
| Point of interconnection | — |
| Requested (queue) date | 2010-04-29 |
| Proposed in-service date | 2011-01-07 |
| Operational date | — |
| Withdrawn date | 2014-01-24 |
| Developer | — |
| Utility / transmission owner | AEC |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-29 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.