Cumberland County, New Jersey — Interconnection Projects
The interXdata warehouse tracks 120 interconnection projects in Cumberland, New Jersey, representing 2,889 MW of requested capacity.
120Total projects
5Active
39Operational
76Withdrawn
2,889 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 21 | 1,693 MW |
| Solar | 90 | 916 MW |
| Battery | 9 | 280 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Churchtown-Cumberland 230kV | S122 | Gas | 478.0 MW | withdrawn | Cumberland, New Jersey |
| Cumberland 230kV | AB2-102 | Gas | 230.0 MW | withdrawn | Cumberland, New Jersey |
| Cumberland (NJ) | 5083_CUMB2 | Gas | 131.8 MW | operational | Cumberland, New Jersey |
| Sherman Avenue | 7288_SEHR | Gas | 112.8 MW | operational | Cumberland, New Jersey |
| Sherman Ave 138kV | U1-029 | Gas | 110.0 MW | withdrawn | Cumberland, New Jersey |
| Cumberland 230 kV | P06 | Gas | 102.0 MW | operational | Cumberland, New Jersey |
| Cumberland (NJ) | 5083_CUMB | Gas | 99.4 MW | operational | Cumberland, New Jersey |
| Cumberland 230 kV | AE2-205 | Solar | 78.0 MW | withdrawn | Cumberland, New Jersey |
| Clayville | 58235_1 | Gas | 73.0 MW | operational | Cumberland, New Jersey |
| Howard Down | 2434_11 | Gas | 68.2 MW | operational | Cumberland, New Jersey |
| Clayville | V2-021 | Gas | 64.0 MW | withdrawn | Cumberland, New Jersey |
| Vineland 69kV | S121 | Gas | 63.0 MW | operational | Cumberland, New Jersey |
| Clayville 69kV | W2-039 | Gas | 63.0 MW | operational | Cumberland, New Jersey |
| South Millville-Newport 69 kV | AE1-179 | Solar | 59.7 MW | withdrawn | Cumberland, New Jersey |
| Cumberland 138 kV | AF2-022 | Battery | 50.0 MW | withdrawn | Cumberland, New Jersey |
| Sherman Ave - West Vineland 69 kV | AF1-238 - moved to TC1 | Battery | 50.0 MW | active | Cumberland, New Jersey |
| South Orchard | AF1-238 | Battery | 50.0 MW | active | Cumberland, New Jersey |
| Landis 138 kV | AE1-161 | Battery | 50.0 MW | withdrawn | Cumberland, New Jersey |
| Carlls Corner-Sherman Avenue 69 kV | AE1-240 | Solar | 49.7 MW | withdrawn | Cumberland, New Jersey |
| Roadstown 69 kV | AG2-241 | Solar | 47.0 MW | withdrawn | Cumberland, New Jersey |
| Newport 69 kV | AE2-091 | Solar | 35.0 MW | withdrawn | Cumberland, New Jersey |
| US Silica-Unimin 69 kV | AG1-001 | Solar | 31.0 MW | withdrawn | Cumberland, New Jersey |
| Sherman Ave 138 kV | AF2-026 | Battery | 30.0 MW | withdrawn | Cumberland, New Jersey |
| Sherman Ave - West Vineland 69 kV | AF1-239 | Battery | 30.0 MW | active | Cumberland, New Jersey |
| Carlls Corner | T63 | Gas | 27.2 MW | withdrawn | Cumberland, New Jersey |
| Newport-South Millville 69kV | V4-036 | Solar | 20.0 MW | withdrawn | Cumberland, New Jersey |
| Millville 12kV | W1-103 | Solar | 20.0 MW | withdrawn | Cumberland, New Jersey |
| Carlls Corner 69kV | W4-041 | Solar | 20.0 MW | withdrawn | Cumberland, New Jersey |
| Silica Spur 2 | W1-118 | Solar | 20.0 MW | withdrawn | Cumberland, New Jersey |
| Fairton 69kV II | W1-022 | Solar | 20.0 MW | withdrawn | Cumberland, New Jersey |
| Millville 2 69kV | W1-086 | Solar | 20.0 MW | withdrawn | Cumberland, New Jersey |
| Stow Creek Township | W2-032 | Solar | 20.0 MW | withdrawn | Cumberland, New Jersey |
| Fairton 69kV I | W1-021 | Solar | 20.0 MW | withdrawn | Cumberland, New Jersey |
| Silica Spur 1 | W1-117 | Solar | 20.0 MW | withdrawn | Cumberland, New Jersey |
| Millville 3 69kV | W1-087 | Solar | 20.0 MW | withdrawn | Cumberland, New Jersey |
| Carll's Corner 69 kV | AF2-020 | Battery | 20.0 MW | withdrawn | Cumberland, New Jersey |
| Millville 1 69kV | W1-085 | Solar | 20.0 MW | withdrawn | Cumberland, New Jersey |
| Millville 4 69kV | W1-088 | Solar | 20.0 MW | withdrawn | Cumberland, New Jersey |
| PJM Queue Project AG2-297 — Solar in Cumberland, New Jersey | AG2-297 | Solar | 19.0 MW | active | Cumberland, New Jersey |
| Cumberland 230 kV | AG2-297 - moved to TC2 | Solar | 19.0 MW | active | Cumberland, New Jersey |
| Newport 69kV | W1-089 | Solar | 18.0 MW | withdrawn | Cumberland, New Jersey |
| Carlls Corner 69kV | U1-066 | Gas | 18.0 MW | withdrawn | Cumberland, New Jersey |
| Vineland | S43 | Gas | 17.0 MW | operational | Cumberland, New Jersey |
| Vineland Solar LLC | 69951_VNLD2 | Solar | 15.0 MW | operational | Cumberland, New Jersey |
| Sherman-Cumberland 138kV | U3-022 | Solar | 14.0 MW | withdrawn | Cumberland, New Jersey |
| Sherman Avenue 69kV | AA2-044 | Solar | 13.5 MW | withdrawn | Cumberland, New Jersey |
| Sherman Ave | T55 | Gas | 12.4 MW | operational | Cumberland, New Jersey |
| Upper Deerfield Township II | V2-044 | Solar | 12.0 MW | withdrawn | Cumberland, New Jersey |
| Upper Deerfield Township I | V2-043 | Solar | 12.0 MW | withdrawn | Cumberland, New Jersey |
| Minotola 12kV | X1-044 | Solar | 10.0 MW | withdrawn | Cumberland, New Jersey |
| Fairton 69kV III | W1-023 | Solar | 10.0 MW | withdrawn | Cumberland, New Jersey |
| Bridgeton 12kV | W2-015 | Solar | 10.0 MW | withdrawn | Cumberland, New Jersey |
| Upper Deerfield | V4-009 | Solar | 10.0 MW | withdrawn | Cumberland, New Jersey |
| U.S. Silica #2 69kV | W4-099 | Solar | 10.0 MW | withdrawn | Cumberland, New Jersey |
| NJ Oak Solar Plant | 57948_OAK | Solar | 10.0 MW | operational | Cumberland, New Jersey |
| Upper Deerfield 12kV | X4-029 | Solar | 10.0 MW | withdrawn | Cumberland, New Jersey |
| Fairfield Township 12kV | V4-054 | Solar | 10.0 MW | operational | Cumberland, New Jersey |
| U.S. Silica #1 69kV | W4-098 | Solar | 10.0 MW | withdrawn | Cumberland, New Jersey |
| Newport 12 kV | AF2-172 | Solar | 10.0 MW | withdrawn | Cumberland, New Jersey |
| Fairton | W3-009 | Solar | 10.0 MW | withdrawn | Cumberland, New Jersey |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Calpine Energy Services, L.P. | 1 | 19 MW |
| Garden Reserve Energy, LLC | 1 | 50 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.