Ouroboros Grid BESS 3 (28INR0403)

Ouroboros Grid BESS 3 is a 200.7 MW other interconnection project in Cameron, Texas with a current status of operational. It is proposed to connect at 88337 Chalybe 345 kV.

200.7 MWCapacity
OperationalStatus
CameronMarket
OtherTechnology

Project facts

Canonical nameOuroboros Grid BESS 3
Queue ID28INR0403
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketCameron
TechnologyOther
Capacity200.7 MW
StateTexas
CountyCameron
Point of interconnection88337 Chalybe 345 kV
Requested (queue) date2025-07-29
Proposed in-service date
Operational date2028-06-01
Withdrawn date
DeveloperOuroboros Grid BESS Unit 6
Utility / transmission ownerERCOT

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata