Ouroboros Grid BESS 5 (28INR0428)
Ouroboros Grid BESS 5 is a 201.0 MW other interconnection project in Cameron, Texas with a current status of operational. It is proposed to connect at 79500 Palmito 345KV.
201.0 MWCapacity
OperationalStatus
CameronMarket
OtherTechnology
Project facts
| Canonical name | Ouroboros Grid BESS 5 |
|---|---|
| Queue ID | 28INR0428 |
| Status | operational |
| Source status | SS Completed, FIS Started, No IA |
| Market | Cameron |
| Technology | Other |
| Capacity | 201.0 MW |
| State | Texas |
| County | Cameron |
| Point of interconnection | 79500 Palmito 345KV |
| Requested (queue) date | 2025-08-18 |
| Proposed in-service date | — |
| Operational date | 2029-06-01 |
| Withdrawn date | — |
| Developer | Ouroboros Grid BESS Unit 6 |
| Utility / transmission owner | ERCOT |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata