Proteus Oak Forest Solar (25INR0461)

Proteus Oak Forest Solar is a 100.0 MW solar interconnection project in Childress, Texas with a current status of withdrawn. It is proposed to connect at 6053 KIRKLAND2A 69Kv.

100.0 MWCapacity
WithdrawnStatus
ERCOTMarket
SolarTechnology

Project facts

Canonical nameProteus Oak Forest Solar
Queue ID25INR0461
Statuswithdrawn
Source statuswithdrawn
MarketERCOT
TechnologySolar
Capacity100.0 MW
StateTexas
CountyChildress
Point of interconnection6053 KIRKLAND2A 69Kv
Requested (queue) date2023-07-30
Proposed in-service date2025-12-31
Operational date
Withdrawn date2024-03-08
DeveloperOak Forest Solar and Storage, LLC (a Delaware LLC)
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.