Red House D.P. 115kV (AH1-056 - moved to TC2)
Red House D.P. 115kV is a 100.0 MW solar interconnection project in Campbell, Virginia with a current status of withdrawn.
100.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology
Project facts
| Canonical name | Red House D.P. 115kV |
|---|---|
| Queue ID | AH1-056 - moved to TC2 |
| Status | withdrawn |
| Source status | Withdrawn |
| Market | — |
| Technology | Solar |
| Capacity | 100.0 MW |
| State | Virginia |
| County | Campbell |
| Point of interconnection | — |
| Requested (queue) date | 2021-07-14 |
| Proposed in-service date | 2030-12-31 |
| Operational date | — |
| Withdrawn date | 2025-12-02 |
| Developer | — |
| Utility / transmission owner | Dominion |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-29 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-28
Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata