Rubi Storage (22INR0510)

Rubi Storage is a 40.0 MW other interconnection project in Hunt, Texas with a current status of withdrawn. It is proposed to connect at 6950 Wallace Switch 138kV.

40.0 MWCapacity
WithdrawnStatus
ERCOTMarket
OtherTechnology

Project facts

Canonical nameRubi Storage
Queue ID22INR0510
Statuswithdrawn
Source statuswithdrawn
MarketERCOT
TechnologyOther
Capacity40.0 MW
StateTexas
CountyHunt
Point of interconnection6950 Wallace Switch 138kV
Requested (queue) date2021-03-17
Proposed in-service date2022-12-31
Operational date
Withdrawn date2021-04-07
DeveloperBelltown Power
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata