SANDSTORM WIND POWER (138)

SANDSTORM WIND POWER is a 150.0 MW wind interconnection project in Riverside, California with a current status of active. It is proposed to connect at Devers Substation 220 kV .

150.0 MWCapacity
ActiveStatus
EasternMarket
WindTechnology

Project facts

Canonical nameSANDSTORM WIND POWER
Queue ID138
Statusactive
Source statusACTIVE
MarketEastern
TechnologyWind
Capacity150.0 MW
StateCalifornia
CountyRiverside
Point of interconnectionDevers Substation 220 kV
Requested (queue) date2006-10-23
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerSCE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectactivehigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.