U.S Silica II 12.47 kV (AG1-300)

U.S Silica II 12.47 kV is a 3.0 MW solar interconnection project in Cumberland, New Jersey with a current status of withdrawn.

3.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameU.S Silica II 12.47 kV
Queue IDAG1-300
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity3.0 MW
StateNew Jersey
CountyCumberland
Point of interconnection
Requested (queue) date2020-09-29
Proposed in-service date2021-12-31
Operational date
Withdrawn date2021-10-01
Developer
Utility / transmission ownerAEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata