Upper Deerfield Township II (V2-044)

Upper Deerfield Township II is a 12.0 MW solar interconnection project in Cumberland, New Jersey with a current status of withdrawn.

12.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameUpper Deerfield Township II
Queue IDV2-044
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity12.0 MW
StateNew Jersey
CountyCumberland
Point of interconnection
Requested (queue) date2009-07-31
Proposed in-service date2010-06-30
Operational date
Withdrawn date2010-03-30
Developer
Utility / transmission ownerAEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.