Vfodnes-Utica Jct. 230kV (GEN-2017-175)

Vfodnes-Utica Jct. 230kV is a 270.0 MW wind interconnection project in Turner, South Dakota with a current status of active. It is proposed to connect at Vfodnes-Utica Jct. 230kV.

270.0 MWCapacity
ActiveStatus
SDMarket
WindTechnology

Project facts

Canonical nameVfodnes-Utica Jct. 230kV
Queue IDGEN-2017-175
Statusactive
Source statusIA FULLY EXECUTED/ON SCHEDULE
MarketSD
TechnologyWind
Capacity270.0 MW
StateSouth Dakota
CountyTurner
Point of interconnectionVfodnes-Utica Jct. 230kV
Requested (queue) date2017-11-29
Proposed in-service date2030-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerWAPA/BEPC/HCPD Integrated System

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.