Wagener 115kV Substation (GEN-2026-SR20)

Wagener 115kV Substation is a 225.0 MW battery interconnection project in Lincoln, Nebraska with a current status of active. It is proposed to connect at Wagener 115kV Substation.

225.0 MWCapacity
ActiveStatus
NEMarket
BatteryTechnology

Project facts

Canonical nameWagener 115kV Substation
Queue IDGEN-2026-SR20
Statusactive
Source statusSPECIAL STUDY
MarketNE
TechnologyBattery
Capacity225.0 MW
StateNebraska
CountyLincoln
Point of interconnectionWagener 115kV Substation
Requested (queue) date2026-03-26
Proposed in-service date2028-06-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerLES

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.