Desoto County, Florida — Interconnection Projects
The interXdata warehouse tracks 37 interconnection projects in Desoto, Florida, representing 2,863 MW of requested capacity.
37Total projects
17Active
16Operational
4Withdrawn
2,863 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 35 | 2,559 MW |
| Battery | 2 | 304 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| FL Queue Project 622 — Battery in Desoto, Florida | 622 | Battery | 300.0 MW | withdrawn | Desoto, Florida |
| FL Queue Project 606 — Solar in Desoto, Florida | 606 | Solar | 74.9 MW | withdrawn | Desoto, Florida |
| FL Queue Project 605 — Solar in Desoto, Florida | 605 | Solar | 74.9 MW | active | Desoto, Florida |
| FL Queue Project 604 — Solar in Desoto, Florida | 604 | Solar | 74.9 MW | active | Desoto, Florida |
| FL Queue Project 471 — Solar in Desoto, Florida | 471 | Solar | 74.5 MW | active | Desoto, Florida |
| Rodeo Solar Center | 62917_1 | Solar | 74.5 MW | operational | DeSoto, Florida |
| Southeast Queue Project 291 — Solar in Desoto, Florida | 291 | Solar | 74.5 MW | operational | Desoto, Florida |
| FL Queue Project 414 — Solar in Desoto, Florida | 414 | Solar | 74.5 MW | active | Desoto, Florida |
| Prairie Creek FL | 65868_1 | Solar | 74.5 MW | operational | DeSoto, Florida |
| FL Queue Project 409 — Solar in Desoto, Florida | 409 | Solar | 74.5 MW | operational | Desoto, Florida |
| Hawthorne Creek | 65926_1 | Solar | 74.5 MW | operational | DeSoto, Florida |
| FL Queue Project 475 — Solar in Desoto, Florida | 475 | Solar | 74.5 MW | active | Desoto, Florida |
| Hog Bay | 65915_1 | Solar | 74.5 MW | operational | DeSoto, Florida |
| FL Queue Project 472 — Solar in Desoto, Florida | 472 | Solar | 74.5 MW | active | Desoto, Florida |
| FL Queue Project 477 — Solar in Desoto, Florida | 477 | Solar | 74.5 MW | active | Desoto, Florida |
| FL Queue Project 430 — Solar in Desoto, Florida | 430 | Solar | 74.5 MW | operational | Desoto, Florida |
| FL Queue Project 474 — Solar in Desoto, Florida | 474 | Solar | 74.5 MW | active | Desoto, Florida |
| FL Queue Project 434 — Solar in Desoto, Florida | 434 | Solar | 74.5 MW | active | Desoto, Florida |
| County Line | 68832_1 | Solar | 74.5 MW | active | DeSoto, Florida |
| Mare Branch | 65905_1 | Solar | 74.5 MW | operational | DeSoto, Florida |
| FL Queue Project 470 — Solar in Desoto, Florida | 470 | Solar | 74.5 MW | withdrawn | Desoto, Florida |
| FL Queue Project 378 — Solar in Desoto, Florida | 378 | Solar | 74.5 MW | operational | Desoto, Florida |
| Cattle Ranch | 62632_1 | Solar | 74.5 MW | operational | DeSoto, Florida |
| FL Queue Project 439 — Solar in Desoto, Florida | 439 | Solar | 74.5 MW | active | Desoto, Florida |
| FL Queue Project 413 — Solar in Desoto, Florida | 413 | Solar | 74.5 MW | active | Desoto, Florida |
| FL Queue Project 429 — Solar in Desoto, Florida | 429 | Solar | 74.5 MW | active | Desoto, Florida |
| FL Queue Project 473 — Solar in Desoto, Florida | 473 | Solar | 74.5 MW | active | Desoto, Florida |
| Joshua Creek | 68835_1 | Solar | 74.5 MW | active | DeSoto, Florida |
| FL Queue Project 476 — Solar in Desoto, Florida | 476 | Solar | 74.5 MW | active | Desoto, Florida |
| Citrus Solar Energy Center Hybrid | 60061_1 | Solar | 74.5 MW | operational | DeSoto, Florida |
| FL Queue Project 377 — Solar in Desoto, Florida | 377 | Solar | 74.5 MW | operational | Desoto, Florida |
| FL Queue Project 381 — Solar in Desoto, Florida | 381 | Solar | 74.5 MW | operational | Desoto, Florida |
| FL Queue Project 521 — Solar in Desoto, Florida | 521 | Solar | 74.5 MW | active | Desoto, Florida |
| FL Queue Project 469 — Solar in Desoto, Florida | 469 | Solar | 74.5 MW | withdrawn | Desoto, Florida |
| Wildflower Solar Energy Center | 61050_1 | Solar | 74.5 MW | operational | Desoto, Florida |
| DeSoto Next Generation Solar Energy | 56929_1 | Solar | 25.0 MW | operational | DeSoto, Florida |
| Citrus Solar Energy Center Hybrid | 60061_BA | Battery | 4.0 MW | operational | DeSoto, Florida |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| FPL | 1 | 74 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); fpl-oasis; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.