Knox And Cedar County, Nebraska — Interconnection Projects
The interXdata warehouse tracks 4 interconnection projects in Knox And Cedar, Nebraska, representing 1,200 MW of requested capacity.
4Total projects
0Active
0Operational
4Withdrawn
1,200 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 4 | 1,200 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| 345kV bus of Turtle Creek Substation | GEN-2021-007 | Wind | 600.0 MW | withdrawn | Knox And Cedar, Nebraska |
| Hoskins 345 kV Substation via Turtle Creek 345 kV Substation | GEN-2023-216 | Wind | 200.0 MW | withdrawn | Knox And Cedar, Nebraska |
| Hoskins 345 kV Substation via Turtle Creek 345 kV Substation | GEN-2023-218 | Wind | 200.0 MW | withdrawn | Knox And Cedar, Nebraska |
| Hoskins 345 kV Substation via Turtle Creek 345 kV Substation | GEN-2023-217 | Wind | 200.0 MW | withdrawn | Knox And Cedar, Nebraska |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Knox And Cedar County.
Start tracking with interXdata