Hand County, South Dakota — Interconnection Projects
The interXdata warehouse tracks 13 interconnection projects in Hand, South Dakota, representing 9,201 MW of requested capacity.
13Total projects
0Active
4Operational
9Withdrawn
9,201 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 10 | 9,025 MW |
| Solar | 1 | 175 MW |
| Battery | 1 | 1 MW |
| Other | 1 | 0 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| MISO Queue Project G705 — Wind in Hand, South Dakota | G705 | Wind | 2,000.0 MW | withdrawn | Hand, South Dakota |
| West Queue Project GI-0612 — Wind in Hand, South Dakota | GI-0612 | Wind | 2,000.0 MW | withdrawn | Hand, South Dakota |
| West Queue Project GI-0611 — Wind in Hand, South Dakota | GI-0611 | Wind | 1,500.0 MW | withdrawn | Hand, South Dakota |
| MISO Queue Project G704 — Wind in Hand, South Dakota | G704 | Wind | 1,500.0 MW | withdrawn | Hand, South Dakota |
| MISO Queue Project G703 — Wind in Hand, South Dakota | G703 | Wind | 1,500.0 MW | withdrawn | Hand, South Dakota |
| Sweetland Wind Farm, LLC | 66496_SLW | Wind | 200.0 MW | operational | Hand, South Dakota |
| Fort Thompson - Huron 230 kV Tap | GEN-2023-154 | Solar | 175.0 MW | withdrawn | Hand, South Dakota |
| West Queue Project GI-0818 — Wind in Hand, South Dakota | GI-0818 | Wind | 150.0 MW | withdrawn | Hand, South Dakota |
| West Queue Project GI-0710 — Wind in Hand, South Dakota | GI-0710 | Wind | 100.0 MW | withdrawn | Hand, South Dakota |
| West Queue Project 40 — Wind in Hand, South Dakota | 40 | Wind | 50.0 MW | operational | Hand, South Dakota |
| Rolling Thunder Wind Farm Hybrid | 57045_1 | Wind | 25.0 MW | operational | Hand, South Dakota |
| Rolling Thunder Wind Farm Hybrid | 57045_2 | Battery | 0.8 MW | operational | Hand, South Dakota |
| Collins HVDC | V4-058 | Other | — | withdrawn | Hand, South Dakota |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue; Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Hand County.