Dickens County, Texas — Interconnection Projects
The interXdata warehouse tracks 18 interconnection projects in Dickens, Texas, representing 3,746 MW of requested capacity.
18Total projects
1Active
14Operational
2Withdrawn
3,746 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Other | 6 | 1,519 MW |
| Solar | 7 | 1,458 MW |
| Wind | 3 | 469 MW |
| Battery | 2 | 300 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| CORRUSCANT BESS | 27INR0195 | Other | 417.8 MW | operational | Dickens, Texas |
| Academy Wind | 25INR0151 | Wind | 304.6 MW | suspended | Dickens, Texas |
| Spurland Solar I | 29INR0192 | Solar | 302.1 MW | operational | Dickens, Texas |
| Outrider BESS | 28INR0288 | Other | 302.0 MW | operational | Dickens, Texas |
| Sanders Hollow Energy Center | 28INR0169 | Other | 292.6 MW | operational | Dickens, Texas |
| Donegal Solar Project | 67543_DOGSP | Solar | 204.2 MW | active | Dickens, Texas |
| Wolf Spring Storage | 25INR0173 | Other | 202.7 MW | operational | Dickens, Texas |
| Spurland Solar II | 29INR0195 | Solar | 201.6 MW | operational | Dickens, Texas |
| Donegal Solar | 23INR0089 | Solar | 201.6 MW | operational | Dickens, Texas |
| Dickens BESS | 22INR0325 | Other | 200.8 MW | operational | Dickens, Texas |
| Timberlakes Solar | 25INR0165 | Solar | 200.7 MW | operational | Dickens, Texas |
| Dickens | 65489_DIKNS | Battery | 200.0 MW | operational | Dickens, Texas |
| Wolf Spring Solar | 25INR0172 | Solar | 195.8 MW | operational | Dickens, Texas |
| AQUAMARINE SOLAR | 21INR0314 | Solar | 151.7 MW | withdrawn | Dickens, Texas |
| McAdoo Wind Energy LLC | 56773_1 | Wind | 150.0 MW | operational | Dickens, Texas |
| Burksol BESS | 23INR0103 | Other | 103.3 MW | operational | Dickens, Texas |
| Burksol Energy Storage | 67968_BES | Battery | 100.0 MW | operational | Dickens, Texas |
| McAdoo repower | 20INR0295 | Wind | 14.7 MW | withdrawn | Dickens, Texas |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Sanders Hollow Energy Center, LLC | 2 | 595 MW |
| Spurland Solar II | 2 | 504 MW |
| Wolf Spring Solar, LLC | 2 | 398 MW |
| BdPU Texas Solar Project II, LLC | 1 | 152 MW |
| HE-Cottonwood Solar LLC | 1 | 202 MW |
| BRP INTERMEDIATECO I LLC | 1 | 201 MW |
| Burksol, LLC | 1 | 103 MW |
| Donegalsol | 1 | 201 MW |
| AEU Battery Project III LLC | 1 | 418 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Dickens County.
Start tracking with interXdata