Terry County, Texas — Interconnection Projects
The interXdata warehouse tracks 6 interconnection projects in Terry, Texas, representing 554 MW of requested capacity.
6Total projects
1Active
0Operational
5Withdrawn
554 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 5 | 504 MW |
| Battery | 1 | 50 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Flatlands 115 kV Substation | GEN-2021-054 | Solar | 150.0 MW | withdrawn | Terry, Texas |
| Flatland 115 kV Substation | GEN-2017-187 | Solar | 150.0 MW | active | Terry, Texas |
| Yoakum-Seagraves 115kV circuit | GEN-2016-090 | Solar | 100.0 MW | withdrawn | Terry, Texas |
| Lakeview-Brownfield 69kV line | GEN-2016-077 | Solar | 54.0 MW | withdrawn | Terry, Texas |
| Terry County 115kV; (Alt. POI) Tap Clauene - Terry County 115kV | GEN-2014-044 | Solar | 50.0 MW | withdrawn | Terry, Texas |
| Flatland 115 kV Substation | GEN-2018-086 | Battery | 50.0 MW | withdrawn | Terry, Texas |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.