Carroll County, Virginia — Interconnection Projects
The interXdata warehouse tracks 18 interconnection projects in Carroll, Virginia, representing 487 MW of requested capacity.
18Total projects
2Active
9Operational
7Withdrawn
487 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 7 | 264 MW |
| Solar+Battery | 2 | 117 MW |
| Wind | 1 | 72 MW |
| Other | 7 | 30 MW |
| Battery | 1 | 4 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Huffman 138 kV | AG2-190 | Solar | 77.4 MW | withdrawn | Carroll, Virginia |
| PJM Queue Project AG2-603 — Solar+Battery in Carroll, Virginia | AG2-603 | Solar+Battery | 77.0 MW | withdrawn | Carroll, Virginia |
| Huffman 138 kV | AG2-603 - moved to TC2 | Solar | 77.0 MW | withdrawn | Carroll, Virginia |
| Jubal Early-Austinville 138kV | Y1-006 | Wind | 72.0 MW | withdrawn | Carroll, Virginia |
| PJM Queue Project AH1-098 — Solar+Battery in Carroll, Virginia | AH1-098 | Solar+Battery | 40.0 MW | active | Carroll, Virginia |
| Wolf Glade-West Carroll 138 kV | AH1-098 - moved to TC2 | Solar | 40.0 MW | active | Carroll, Virginia |
| Wolf Glade 34.5 kV | AH1-172 | Solar | 20.0 MW | withdrawn | Carroll, Virginia |
| Jubal Early - Pipers Gap 138 kV | AH1-097 | Solar | 20.0 MW | withdrawn | Carroll, Virginia |
| River Trail Solar, LLC | 67218_ENX22 | Solar | 20.0 MW | operational | Carroll, Virginia |
| Willis Gap 34.5 kV | AH1-177 | Solar | 10.0 MW | withdrawn | Carroll, Virginia |
| Byllesby 2 | 3773_1 | Other | 5.4 MW | operational | Carroll, Virginia |
| Byllesby 2 | 3773_4 | Other | 5.4 MW | operational | Carroll, Virginia |
| Byllesby 2 | 3773_3 | Other | 5.4 MW | operational | Carroll, Virginia |
| Byllesby 2 | 3773_2 | Other | 5.4 MW | operational | Carroll, Virginia |
| Byllesby 69 kV | AD2-205 | Battery | 4.0 MW | operational | Carroll, Virginia |
| Buck Hydro | 3772_3 | Other | 2.8 MW | operational | Carroll, Virginia |
| Buck Hydro | 3772_2 | Other | 2.8 MW | operational | Carroll, Virginia |
| Buck Hydro | 3772_1 | Other | 2.8 MW | operational | Carroll, Virginia |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Issa Solar LLC | 1 | 77 MW |
| Pine Branch Solar, LLC | 1 | 40 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Carroll County.
Start tracking with interXdata