San Diego Gas & Electric Co — Interconnection Queue Projects
San Diego Gas & Electric Co is associated with 22 tracked interconnection projects representing 933 MW of requested capacity.
Entity resolution: single source organization name; no cluster merge applied.
22Projects
0Active
22Operational
0Withdrawn
933 MWRequested capacity
0Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 6 | 714 MW |
| Battery | 15 | 215 MW |
| Solar | 1 | 4 MW |
Geographic footprint
| State | Projects |
|---|---|
| California | 22 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Palomar Energy | 55985_STG | Gas | 229.0 MW | operational | San Diego, California |
| Palomar Energy | 55985_CTG1 | Gas | 165.0 MW | operational | San Diego, California |
| Palomar Energy | 55985_CTG2 | Gas | 165.0 MW | operational | San Diego, California |
| Miramar Energy Facility | 56232_1 | Gas | 53.0 MW | operational | San Diego, California |
| Miramar Energy Facility | 56232_2 | Gas | 53.0 MW | operational | San Diego, California |
| Cuyamaca Peak Energy Plant | 55512_CPP6 | Gas | 48.7 MW | operational | San Diego, California |
| Fallbrook Energy Storage | 61365_FBES | Battery | 40.0 MW | operational | San Diego, California |
| Escondido Energy Storage | 60570_SES | Battery | 30.0 MW | operational | San Diego, California |
| Top Gun Energy Storage | 61366_TGES | Battery | 30.0 MW | operational | San Diego, California |
| Pala Gomez Creek BESS | 66280_1 | Battery | 10.0 MW | operational | San Diego, California |
| Boulevard Energy Storage | 66279_1 | Battery | 10.0 MW | operational | San Diego, California |
| Kearny North Energy Storage | 64612_KNES | Battery | 10.0 MW | operational | San Diego, California |
| Melrose BESS | 66281_1 | Battery | 10.0 MW | operational | San Diego, California |
| Clairemont Energy Storage | 66266_1 | Battery | 10.0 MW | operational | San Diego, California |
| Melrose BESS | 66281_2 | Battery | 10.0 MW | operational | San Diego, California |
| Elliott Energy Storage | 66278_1 | Battery | 10.0 MW | operational | San Diego, California |
| Santee BESS | 67118_1 | Battery | 10.0 MW | operational | San Diego, California |
| Paradise Energy Storage | 66265_1 | Battery | 10.0 MW | operational | San Diego, California |
| Kearny South Energy Storage | 64614_KSES | Battery | 10.0 MW | operational | San Diego, California |
| El Cajon Energy Storage | 60569_SES | Battery | 7.5 MW | operational | San Diego, California |
| Dark Sky Energy Center | 66599_1 | Battery | 7.3 MW | operational | San Diego, California |
| Ramona Solar Energy | 60995_1 | Solar | 4.3 MW | operational | San Diego, California |
Recent material changes
No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.