WAPA-MPP — Interconnection Queue Projects

WAPA-MPP is associated with 4 tracked interconnection projects representing 2,100 MW of requested capacity.

Entity resolution: single source organization name; no cluster merge applied.

4Projects
4Active
0Operational
0Withdrawn
2,100 MWRequested capacity
0Markets

Capacity by technology

TechnologyProjectsRequested capacity
Solar+Battery21,100 MW
Battery21,000 MW

Geographic footprint

StateProjects
Arizona4

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
West Queue Project 2023-MP2 — Solar+Battery in Mohave, Arizona2023-MP2Solar+Battery600.0 MWactiveMohave, Arizona
West Queue Project 2024-MP1 — Battery in Mohave, Arizona2024-MP1Battery500.0 MWactiveMohave, Arizona
West Queue Project 2024-MP2 — Battery in Mohave, Arizona2024-MP2Battery500.0 MWactiveMohave, Arizona
West Queue Project 2023-MP1 — Solar+Battery in Yavapai, Arizona2023-MP1Solar+Battery500.0 MWactiveYavapai, Arizona

Recent material changes

No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Track queue activity connecting through WAPA-MPP.

Start tracking with interXdata