Tolland County, Connecticut — Interconnection Projects
The interXdata warehouse tracks 33 interconnection projects in Tolland, Connecticut, representing 125 MW of requested capacity.
33Total projects
2Active
26Operational
5Withdrawn
125 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 6 | 61 MW |
| Solar | 16 | 54 MW |
| Solar+Battery | 1 | 11 MW |
| Battery | 10 | 0 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| UCONN COGEN Facility | 110 | Gas | 24.9 MW | operational | Tolland, Connecticut |
| EE Mansfield Center DG Cluster | 1490 | Solar | 20.0 MW | withdrawn | Tolland, Connecticut |
| EE Mansfield Center DG Cluster | 1489 | Solar+Battery | 10.8 MW | withdrawn | Tolland, Connecticut |
| CT additional | 895 | Gas | 10.0 MW | withdrawn | Tolland, Connecticut |
| UCONN Cogen Facility | 58159_CGT2 | Gas | 6.9 MW | operational | Tolland, Connecticut |
| UCONN Cogen Facility | 58159_CGT3 | Gas | 6.9 MW | operational | Tolland, Connecticut |
| UCONN Cogen Facility | 58159_CGT1 | Gas | 6.9 MW | operational | Tolland, Connecticut |
| UCONN Cogen Facility | 58159_STG1 | Gas | 5.0 MW | operational | Tolland, Connecticut |
| Somers Solar Center, LLC | 58554_1 | Solar | 5.0 MW | operational | Tolland, Connecticut |
| USS Vineyard Solar, Somers Rd | 1199 | Solar | 4.0 MW | withdrawn | Tolland, Connecticut |
| Stafford Solar One | 69282_STFRD | Solar | 4.0 MW | operational | Tolland, Connecticut |
| Community Power Group, 24 Middle Road, Ellington, CT | 1202 | Solar | 4.0 MW | withdrawn | Tolland, Connecticut |
| Barrow Solar | 65287_BARRO | Solar | 2.0 MW | operational | Tolland, Connecticut |
| Bilton Solar | 69447_BILT | Solar | 2.0 MW | operational | Tolland, Connecticut |
| Ellington - 277 Sadds Mill | 67865_10634 | Solar | 2.0 MW | operational | Tolland, Connecticut |
| CTGB Maloney and Webster | 69013_GBMWP | Solar | 2.0 MW | operational | Tolland, Connecticut |
| Mansfield Landfill | 69515_MNSFL | Solar | 1.8 MW | operational | Tolland, Connecticut |
| CTGB Osborn | 69012_GBOPV | Solar | 1.8 MW | operational | Tolland, Connecticut |
| Blair Solar | 64217_BLAIR | Solar | 1.0 MW | operational | Tolland, Connecticut |
| Madison Solar (CT) | 64218_MADIS | Solar | 1.0 MW | operational | Tolland, Connecticut |
| Stafford MS Ground Mount Community Solar | 60880_MS1 | Solar | 1.0 MW | operational | Tolland, Connecticut |
| Stafford MS Ground Mount Community Solar | 60880_MS2 | Solar | 1.0 MW | operational | Tolland, Connecticut |
| Few Solar | 64219_FEW | Solar | 1.0 MW | operational | Tolland, Connecticut |
| Eversource Storage ESS-00026 | ESS-00026 | Battery | 0.1 MW | operational | Tolland, Connecticut |
| Eversource Storage ESS-00482 | ESS-00482 | Battery | 0.0 MW | active | Tolland, Connecticut |
| Eversource Storage ESS-00395 | ESS-00395 | Battery | 0.0 MW | operational | Tolland, Connecticut |
| Eversource Storage ESS-00473 | ESS-00473 | Battery | 0.0 MW | operational | Tolland, Connecticut |
| Eversource Storage ESS-00187 | ESS-00187 | Battery | 0.0 MW | operational | Tolland, Connecticut |
| Eversource Storage ESS-00188 | ESS-00188 | Battery | 0.0 MW | active | Tolland, Connecticut |
| Eversource Storage ESS-00117 | ESS-00117 | Battery | 0.0 MW | operational | Tolland, Connecticut |
| Eversource Storage ESS-00520 | ESS-00520 | Battery | 0.0 MW | operational | Tolland, Connecticut |
| Eversource Storage ESS-00516 | ESS-00516 | Battery | 0.0 MW | operational | Tolland, Connecticut |
| Eversource Storage ESS-00513 | ESS-00513 | Battery | 0.0 MW | operational | Tolland, Connecticut |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Earthlight Technologies, LLC | 4 | 0 MW |
| SAVKAT, Inc. | 2 | 0 MW |
| Synergy Smart Homes | 2 | 0 MW |
| Powur PBC | 1 | 0 MW |
| CES Danbury LLC DBA Ross Solar Group | 1 | 0 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: ct-ess-storage; U.S. EIA — Form EIA-860M generator inventory (operating + planned); isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Tolland County.