Volusia County, Florida — Interconnection Projects
The interXdata warehouse tracks 34 interconnection projects in Volusia, Florida, representing 9,841 MW of requested capacity.
34Total projects
1Active
24Operational
8Withdrawn
9,841 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 22 | 9,130 MW |
| Other | 8 | 486 MW |
| Solar | 4 | 225 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Southeast Queue Project 143 — Gas in Volusia, Florida | 143 | Gas | 1,180.0 MW | withdrawn | Volusia, Florida |
| FL Queue Project 027074 — Gas in Volusia, Florida | 027074 | Gas | 1,180.0 MW | withdrawn | Volusia, Florida |
| FL Queue Project 027058 — Gas in Volusia, Florida | 027058 | Gas | 1,174.0 MW | withdrawn | Volusia, Florida |
| Southeast Queue Project 157 — Gas in Volusia, Florida | 157 | Gas | 1,174.0 MW | withdrawn | Volusia, Florida |
| Southeast Queue Project 156 — Gas in Volusia, Florida | 156 | Gas | 655.0 MW | withdrawn | Volusia, Florida |
| FL Queue Project 027056 — Gas in Volusia, Florida | 027056 | Gas | 655.0 MW | withdrawn | Volusia, Florida |
| Sanford | 620_5 | Gas | 436.1 MW | operational | Volusia, Florida |
| Sanford | 620_4 | Gas | 436.1 MW | operational | Volusia, Florida |
| Sanford | 620_4C | Gas | 188.2 MW | operational | Volusia, Florida |
| Sanford | 620_5D | Gas | 188.2 MW | operational | Volusia, Florida |
| Sanford | 620_4D | Gas | 188.2 MW | operational | Volusia, Florida |
| Sanford | 620_5B | Gas | 188.2 MW | operational | Volusia, Florida |
| Sanford | 620_5A | Gas | 188.2 MW | operational | Volusia, Florida |
| Sanford | 620_5C | Gas | 188.2 MW | operational | Volusia, Florida |
| Sanford | 620_4B | Gas | 188.2 MW | operational | Volusia, Florida |
| Sanford | 620_4A | Gas | 188.2 MW | operational | Volusia, Florida |
| Southeast Queue Project 12 — Gas in Volusia, Florida | 12 | Gas | 182.0 MW | withdrawn | Volusia, Florida |
| Duke Energy Florida, LLC | 027120 | Gas | 182.0 MW | withdrawn | Volusia, Florida |
| DeBary | 6046_8 | Gas | 103.5 MW | operational | Volusia, Florida |
| DeBary | 6046_9 | Gas | 103.5 MW | operational | Volusia, Florida |
| DeBary | 6046_10 | Other | 103.5 MW | operational | Volusia, Florida |
| DeBary | 6046_7 | Gas | 103.5 MW | operational | Volusia, Florida |
| Debary Solar Power Plant | 62542_PV1 | Solar | 74.5 MW | operational | Volusia, Florida |
| Duke Energy Florida, LLC | 020384 | Solar | 74.5 MW | active | Volusia, Florida |
| Pioneer Trail Solar Energy Center | 61767_1 | Solar | 74.5 MW | operational | Volusia, Florida |
| DeBary | 6046_4 | Other | 66.8 MW | operational | Volusia, Florida |
| DeBary | 6046_5 | Other | 66.8 MW | operational | Volusia, Florida |
| DeBary | 6046_3 | Other | 66.8 MW | operational | Volusia, Florida |
| DeBary | 6046_6 | Other | 66.8 MW | operational | Volusia, Florida |
| DeBary | 6046_2 | Other | 66.8 MW | operational | Volusia, Florida |
| FL Queue Project 417 — Gas in Volusia, Florida | 417 | Gas | 60.0 MW | operational | Volusia, Florida |
| Field Street | 7954_1 | Other | 24.0 MW | suspended | Volusia, Florida |
| Field Street | 7954_2 | Other | 24.0 MW | operational | Volusia, Florida |
| Daytona International Speedway Solar | 60005_1 | Solar | 1.6 MW | operational | Volusia, Florida |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Duke Energy Florida, LLC | 3 | 438 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: duke-def-oasis; U.S. EIA — Form EIA-860M generator inventory (operating + planned); fpl-oasis; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Volusia County.