Benton County, Indiana — Interconnection Projects
The interXdata warehouse tracks 35 interconnection projects in Benton, Indiana, representing 6,359 MW of requested capacity.
35Total projects
1Active
19Operational
15Withdrawn
6,359 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 32 | 5,984 MW |
| Battery | 2 | 225 MW |
| Solar | 1 | 150 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Olive-Dequine 345kv | Q01 | Wind | 500.0 MW | operational | Benton, Indiana |
| Dequine 345 kV | AD1-137 | Wind | 500.0 MW | withdrawn | Benton, Indiana |
| MISO Queue Project G656 — Wind in Benton, Indiana | G656 | Wind | 500.0 MW | withdrawn | Benton, Indiana |
| Dequine 345 kV | AD2-015 | Wind | 500.0 MW | withdrawn | Benton, Indiana |
| MISO Queue Project J515 — Wind in Benton, Indiana | J515 | Wind | 400.0 MW | operational | Benton, Indiana |
| Cayuga sub (Jordan Creek Wind J515 POI) 345 kV | J2241 | Wind | 320.0 MW | withdrawn | Benton, Indiana |
| MISO Queue Project G666 — Wind in Benton, Indiana | G666 | Wind | 250.0 MW | withdrawn | Benton, Indiana |
| Olive-Dequine 345kV | Q03 | Wind | 250.0 MW | operational | Benton, Indiana |
| MISO Queue Project G865 — Wind in Benton, Indiana | G865 | Wind | 201.0 MW | withdrawn | Benton, Indiana |
| Meadow Lake Wind Farm VI LLC | 61756_MWLVI | Wind | 200.4 MW | operational | Benton, Indiana |
| Templeton Wind | 68179_TEMPW | Wind | 200.2 MW | active | Benton, Indiana |
| Fowler Ridge Wind Farm LLC | 56777_FII | Wind | 200.0 MW | operational | Benton, Indiana |
| Olive-Dequine 345kV | T126 | Wind | 200.0 MW | operational | Benton, Indiana |
| Dequine 345kV | U1-087 | Wind | 150.0 MW | withdrawn | Benton, Indiana |
| Fowler Ridge IV Wind Farm LLC | 59547_1 | Wind | 150.0 MW | operational | Benton, Indiana |
| Fowler Ridge 345 kV | AH1-595 | Solar | 150.0 MW | withdrawn | Benton, Indiana |
| Benton County Wind Farm | 56679_1 | Wind | 130.5 MW | operational | Benton, Indiana |
| Fowler Ridge 345 kV | AH1-596 | Battery | 125.0 MW | withdrawn | Benton, Indiana |
| MISO Queue Project G616 — Wind in Benton, Indiana | G616 | Wind | 120.0 MW | withdrawn | Benton, Indiana |
| Hoosier Wind Project LLC | 56878_TBD | Wind | 106.0 MW | operational | Benton, Indiana |
| Fowler Ridge Wind Farm LLC | 56777_FIA | Wind | 101.3 MW | operational | Benton, Indiana |
| MISO Queue Project J431 — Wind in Benton, Indiana | J431 | Wind | 100.0 MW | operational | Benton, Indiana |
| Dequine 345kV | U1-088 | Wind | 100.0 MW | withdrawn | Benton, Indiana |
| MISO Queue Project G439 — Wind in Benton, Indiana | G439 | Wind | 100.0 MW | operational | Benton, Indiana |
| GOODLAND - MORRISON DITCH 138.0kV | J2048 | Wind | 100.0 MW | operational | Benton, Indiana |
| MISO Queue Project N001 — Wind in Benton, Indiana | N001 | Wind | 100.0 MW | operational | Benton, Indiana |
| GOODLAND - MORRISON DITCH 138.0kV | J2440 | Wind | 100.0 MW | operational | Benton, Indiana |
| Wilton Center-Loretto | AE1-002 | Battery | 100.0 MW | withdrawn | Benton, Indiana |
| Fowler Ridge Wind Farm LLC | 56777_FIB | Wind | 100.0 MW | operational | Benton, Indiana |
| Fowler Ridge Wind Farm LLC | 56777_FIII | Wind | 99.0 MW | operational | Benton, Indiana |
| Fowler Ridge Wind Farm LLC | 56777_FIC | Wind | 88.0 MW | operational | Benton, Indiana |
| MISO Queue Project G888 — Wind in Benton, Indiana | G888 | Wind | 50.0 MW | withdrawn | Benton, Indiana |
| MISO Queue Project G606 — Wind in Benton, Indiana | G606 | Wind | 30.0 MW | operational | Benton, Indiana |
| MISO Queue Project G887 — Wind in Benton, Indiana | G887 | Wind | 20.0 MW | withdrawn | Benton, Indiana |
| MISO Queue Project G969 — Wind in Benton, Indiana | G969 | Wind | 18.0 MW | withdrawn | Benton, Indiana |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; MISO — generator interconnection queue; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.