Cheyenne County, Nebraska — Interconnection Projects
The interXdata warehouse tracks 9 interconnection projects in Cheyenne, Nebraska, representing 1,480 MW of requested capacity.
9Total projects
1Active
1Operational
7Withdrawn
1,480 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 4 | 1,048 MW |
| Solar | 5 | 433 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Sidney (SIDNEY__-MB3) 345 kV Substation | GEN-2024-151 | Wind | 300.0 MW | withdrawn | Cheyenne, Nebraska |
| Sidney (SIDNEY__-MB3) 345 kV Substation | GEN-2024-150 | Wind | 293.6 MW | withdrawn | Cheyenne, Nebraska |
| Sidney (SIDNEY__-MB3) 345 kV Substation | GEN-2024-152 | Wind | 250.1 MW | withdrawn | Cheyenne, Nebraska |
| West Queue Project GI-0815 — Wind in Cheyenne, Nebraska | GI-0815 | Wind | 204.0 MW | withdrawn | Cheyenne, Nebraska |
| Sidney Substation 230kV | GEN-2016-079 | Solar | 160.0 MW | withdrawn | Cheyenne, Nebraska |
| Sidney - Stegall 230 kV | GEN-2022-028 | Solar | 125.0 MW | withdrawn | Cheyenne, Nebraska |
| Sidney 230 kV | GEN-2019-042 | Solar | 104.0 MW | withdrawn | Cheyenne, Nebraska |
| Sidney 115 kV Sub | GEN-2016-147 | Solar | 40.0 MW | active | Cheyenne, Nebraska |
| Sidney Solar | 70129_GEN1 | Solar | 3.8 MW | operational | Cheyenne, Nebraska |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.