The interXdata warehouse tracks 26 interconnection projects in Castro, Texas, representing 6,832 MW of requested capacity.
26Total projects
4Active
12Operational
6Withdrawn
6,832 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 17 | 3,928 MW |
| Solar | 6 | 1,710 MW |
| Other | 3 | 1,194 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Cavell Wind | 29INR0035 | Other | 641.2 MW | operational | Castro, Texas |
| Cavell Solar | 29INR0034 | Solar | 502.1 MW | operational | Castro, Texas |
| Castro 115kV | GEN-2014-040 | Wind | 320.0 MW | operational | Castro, Texas |
| Easter Wind | 15INR0063 | Wind | 307.5 MW | withdrawn | Castro, Texas |
| Acker BESS | 25INR0460 | Other | 301.0 MW | operational | Castro, Texas |
| Newhart 230kV Substation | GEN-2022-199 | Wind | 300.0 MW | withdrawn | Castro, Texas |
| Olson 230 kV Substation | GEN-2024-050 | Solar | 300.0 MW | withdrawn | Castro, Texas |
| Newhart 230 kV Substation | GEN-2024-099 | Solar | 300.0 MW | operational | Castro, Texas |
| Newhart 230 kV Substation | GEN-2024-100 | Wind | 300.0 MW | withdrawn | Castro, Texas |
| Shifting Gale Wind | 19INR0175 | Wind | 289.0 MW | suspended | Castro, Texas |
| Changing Winds | 59243_CHAN1 | Wind | 288.0 MW | active | Castro, Texas |
| Bethel Wind Farm LLC | 60414_GEN1 | Wind | 276.0 MW | operational | Castro, Texas |
| Ogalalla Storage | 27INR0143 | Other | 251.6 MW | operational | Castro, Texas |
| Newhart 230kV Substation | GEN-2022-216 | Wind | 250.0 MW | withdrawn | Castro, Texas |
| Castro Solar | 20INR0050 | Solar | 224.7 MW | operational | Castro, Texas |
| Nazareth Solar | 16INR0049 | Solar | 203.0 MW | operational | Castro, Texas |
| Cattleman Wind A | 16INR0014 | Wind | 201.6 MW | suspended | Castro, Texas |
| Cattleman Wind B | 16INR0014b | Wind | 201.6 MW | suspended | Castro, Texas |
| GEN-2007-010 | GEN-2007-010 | Wind | 200.0 MW | withdrawn | Castro, Texas |
| Newhart 230kV Substation | GEN-2018-089 | Wind | 196.0 MW | active | Castro, Texas |
| Scarlet Solar | 23INR0015 | Solar | 180.0 MW | operational | Castro, Texas |
| Hart Wind | 67763_5932 | Wind | 166.4 MW | operational | Castro, Texas |
| Hart Wind (Old POI) | 16INR0033 | Wind | 165.0 MW | suspended | Castro, Texas |
| Hart Wind | 24INR0116 | Wind | 163.4 MW | operational | Castro, Texas |
| Easter | 59971_ESTR1 | Wind | 152.0 MW | active | Castro, Texas |
| Deaf Smith-Plant X 230kV | GEN-2017-146 | Wind | 151.8 MW | active | Castro, Texas |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| IP Cavell, LLC | 2 | 1,143 MW |
| RWE Solar Development, LLC | 2 | 403 MW |
| Hecate Energy | 1 | 252 MW |
| Ogallala BESS LLC | 1 | 301 MW |
| Castro Solar One, LLC | 1 | 225 MW |
| Hart Wind Project, LLC | 1 | 163 MW |
| TX Nazareth Solar, LLC | 1 | 203 MW |
| TriGlobal | 1 | 308 MW |
| Innovative Solar 245, LLC | 1 | 180 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Castro County.
Start tracking with interXdata