Kenedy County, Texas — Interconnection Projects
The interXdata warehouse tracks 13 interconnection projects in Kenedy, Texas, representing 3,062 MW of requested capacity.
13Total projects
0Active
10Operational
1Withdrawn
3,062 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 9 | 1,752 MW |
| Other | 2 | 701 MW |
| Solar | 2 | 609 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Tall Saddle Wind | 27INR0310 | Other | 522.8 MW | operational | Kenedy, Texas |
| Green Ocelot Solar | 28INR0180 | Solar | 357.0 MW | operational | Kenedy, Texas |
| Pattern Gulf Wind | 56661_1 | Wind | 283.2 MW | operational | Kenedy, Texas |
| Tall Saddle Solar | 27INR0309 | Solar | 252.3 MW | operational | Kenedy, Texas |
| Gulf Wind 2 | 20INR0043 | Wind | 226.5 MW | suspended | Kenedy, Texas |
| Penascal II Wind Project LLC | 57095_1 | Wind | 201.6 MW | operational | Kenedy, Texas |
| Penascal Wind Power LLC | 56795_1 | Wind | 201.6 MW | operational | Kenedy, Texas |
| Stella 1 Wind | 15INR0035 | Wind | 201.0 MW | operational | Kenedy, Texas |
| Stella 2 Wind | 16INR0012 | Wind | 201.0 MW | suspended | Kenedy, Texas |
| Stella Wind Farm | 59063_WT1 | Wind | 201.0 MW | operational | Kenedy, Texas |
| Baffin Wind | 57927_1 | Wind | 188.0 MW | operational | Kenedy, Texas |
| Green Ocelot Storage | 28INR0189 | Other | 178.5 MW | operational | Kenedy, Texas |
| Gulf Wind 2 Expansion | 20INR0260 | Wind | 47.9 MW | withdrawn | Kenedy, Texas |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Eon | 2 | 402 MW |
| Ocelot Solar LLC | 2 | 536 MW |
| Tall Saddle Solar, LLC | 1 | 252 MW |
| Texas GULF WIND 2 LLC | 1 | 48 MW |
| Tall Saddle Wind, LLC | 1 | 523 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Kenedy County.
Start tracking with interXdata