Live Oak County, Texas — Interconnection Projects

The interXdata warehouse tracks 7 interconnection projects in Live Oak, Texas, representing 531 MW of requested capacity.

7Total projects
0Active
5Operational
1Withdrawn
531 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Solar5430 MW
Other2101 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Urca Solar24INR0292Solar204.1 MWsuspendedLive Oak, Texas
Anagram Solar25INR0621Solar130.6 MWoperationalLive Oak, Texas
Bird Dog Energy Storage22INR0467Other60.4 MWoperationalLive Oak, Texas
Brightside Solar Alt POI23INR0487Solar50.0 MWoperationalLive Oak, Texas
Buck Ranch Solar SLF27INR0375Solar40.8 MWoperationalLive Oak, Texas
Buck Ranch Storage SLF27INR0376Other40.8 MWoperationalLive Oak, Texas
CITY WEST Solar20INR0283Solar4.1 MWwithdrawnLive Oak, Texas

Top developers

Developer (canonical)ProjectsCapacity
Buck Ranch Solar, LLC282 MW
VESI 37 LLC160 MW
MERIT SI DEVELOPMENT, LLC14 MW
Anagram Solar1131 MW
Brightside Solar, LLC150 MW

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Get an alert when a new project is proposed in Live Oak County.