Runnels County, Texas — Interconnection Projects
The interXdata warehouse tracks 12 interconnection projects in Runnels, Texas, representing 2,728 MW of requested capacity.
12Total projects
0Active
9Operational
3Withdrawn
2,728 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 8 | 1,834 MW |
| Other | 4 | 894 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Mistflower Energy Center Solar | 30INR0088 | Solar | 401.6 MW | operational | Runnels, Texas |
| Dexter Solar | 22INR0213 | Solar | 330.1 MW | withdrawn | Runnels, Texas |
| Dexter Storage | 21INR0412 | Other | 325.0 MW | withdrawn | Runnels, Texas |
| Mistflower Energy Center Storage | 30INR0089 | Other | 312.9 MW | operational | Runnels, Texas |
| Winters Glow Solar | 28INR0198 | Solar | 301.6 MW | operational | Runnels, Texas |
| Zuma Solar | 30INR0076 | Solar | 201.4 MW | operational | Runnels, Texas |
| Sawtooth Solar | 29INR0210 | Solar | 201.4 MW | operational | Runnels, Texas |
| Winters Glow Storage | 28INR0199 | Other | 155.2 MW | operational | Runnels, Texas |
| Wagon Wheel Solar | 21INR0377 | Solar | 144.8 MW | withdrawn | Runnels, Texas |
| Norton Solar | 19INR0035 | Solar | 128.5 MW | operational | Runnels, Texas |
| Norton Solar Farm | 61967_NSM01 | Solar | 125.0 MW | operational | Runnels, Texas |
| Rutile BESS | 24INR0485 | Other | 100.7 MW | operational | Runnels, Texas |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Mistflower Energy Center LLC | 2 | 714 MW |
| 241BB 8ME LLC | 2 | 655 MW |
| TAI Norton Solar, LLC | 1 | 128 MW |
| Rutile BESS, LLC | 1 | 101 MW |
| Orion Power Generation, LLC | 1 | 145 MW |
| Zuma Solar, LLC | 1 | 201 MW |
| Winters Glow Storage, LLC | 1 | 155 MW |
| Winters Glow Solar, LLC | 1 | 302 MW |
| Sawtooth Solar, LLC | 1 | 201 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Runnels County.