SPEC — Interconnection Queue Projects
SPEC is associated with 6 tracked interconnection projects representing 30 MW of requested capacity.
Entity resolution: single source organization name; no cluster merge applied.
6Projects
0Active
1Operational
4Withdrawn
30 MWRequested capacity
0Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Other | 1 | 15 MW |
| Wind | 4 | 10 MW |
| Gas | 1 | 6 MW |
Geographic footprint
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Russell 115 kV substaition | AFS NJG-2026-004 | Other | 15.0 MW | unknown | Russell, Kansas |
| 34.5kV Substation. Nearest transmission bus: 115kV Bluejay | AFS NJG-2026-003 | Gas | 6.0 MW | operational | Cimarron, Kansas |
| Wolfforth 12.47 kV Substation | ASGI-2016-009 | Wind | 3.0 MW | withdrawn | — |
| Wolfforth 115kV substation #526524 | ASGI-2016-001 | Wind | 2.5 MW | withdrawn | Lubbock County, Texas |
| Yuma Delivery Point | ASGI-2015-002 | Wind | 2.0 MW | withdrawn | Lubbock County, Texas |
| Erskine 115kV bus | ASGI-2014-013 | Wind | 2.0 MW | withdrawn | Lubbock County, Texas |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-08-19 | Russell 115 kV substaition | new_project | — | unknown |
| 2026-08-19 | 34.5kV Substation. Nearest transmission bus: 115kV Bluejay | new_project | — | operational |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Track queue activity connecting through SPEC.