ODEC — Interconnection Queue Projects
ODEC is associated with 32 tracked interconnection projects representing 740 MW of requested capacity.
Entity resolution: single source organization name; no cluster merge applied.
32Projects
0Active
4Operational
28Withdrawn
740 MWRequested capacity
0Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 20 | 478 MW |
| Wind | 4 | 168 MW |
| Battery | 5 | 65 MW |
| Gas | 3 | 29 MW |
Geographic footprint
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Oak Hall 138kV | W3-054A | Wind | 95.0 MW | withdrawn | Accomack, Virginia |
| Belle Haven-Tasley 69 kV | AE1-192 | Solar | 70.0 MW | withdrawn | Accomack, Virginia |
| Tasley - Oak Hall 69 kV | AG1-429 | Solar | 58.7 MW | withdrawn | Accomack, Virginia |
| Tasley-Kellam 69kV | Y1-008 | Wind | 50.0 MW | withdrawn | Accomack, Virginia |
| Plaintation Creek 69 kV | AF2-055 | Solar | 45.0 MW | withdrawn | Northampton, Virginia |
| Tasley-Oak Hall 69kV II | AB2-192 | Solar | 20.0 MW | withdrawn | Accomack, Virginia |
| Oak Hall-Hallwood 69 kV | AG2-103 | Solar | 20.0 MW | withdrawn | Accomack, Virginia |
| Tasley-Kellam 69kV | V4-064 | Solar | 20.0 MW | withdrawn | Accomack, Virginia |
| Tasley-Oak Hall 69kV I | AB2-165 | Solar | 20.0 MW | withdrawn | Accomack, Virginia |
| Tasley-Kellam 69kV | W1-009 | Solar | 20.0 MW | withdrawn | Accomack, Virginia |
| Tasley 69kV | AH2-050 | Battery | 20.0 MW | withdrawn | Accomack, Virginia |
| Bayview 69kV | AH2-048 | Battery | 20.0 MW | withdrawn | Northampton, Virginia |
| Tasley-Kellam 69kV | W1-008 | Solar | 20.0 MW | withdrawn | Accomack, Virginia |
| Kellam - Bayview 69kV | X4-014 | Battery | 20.0 MW | withdrawn | Northampton, Virginia |
| Weirwood-Eastville 69kV | Z2-012 | Solar | 20.0 MW | operational | Northampton, Virginia |
| Bayview | V2-045 | Solar | 20.0 MW | withdrawn | Northampton, Virginia |
| Wallops Island 69 kV | AE1-145 | Solar | 20.0 MW | withdrawn | Accomack, Virginia |
| Wattsville-Wallops Island 69kV | AB2-164 | Solar | 20.0 MW | withdrawn | Accomack, Virginia |
| Greenbush 69kV | AH1-169 | Solar | 20.0 MW | withdrawn | Accomack, Virginia |
| Oak Hall-Perdue 69 kV | AG2-102 | Solar | 20.0 MW | withdrawn | Accomack, Virginia |
| Rock Springs | R20 | Gas | 20.0 MW | operational | Cecil, Maryland |
| Bayview | V3-061 | Solar | 20.0 MW | withdrawn | Northampton, Virginia |
| Tasley 69kV | AC1-009 | Solar | 20.0 MW | withdrawn | Accomack, Virginia |
| Weirwood-Eastville 69kV | X3-040 | Wind | 18.0 MW | withdrawn | Northampton, Virginia |
| Tasley 69kV | AB2-033 | Solar | 10.0 MW | withdrawn | Accomack, Virginia |
| Tasley 69kV | AC1-052 | Solar | 9.0 MW | withdrawn | Accomack, Virginia |
| Rock Springs 500kV | U4-015 | Gas | 8.7 MW | operational | Cecil, Maryland |
| Tasley 25 kV | AF1-243 | Battery | 5.0 MW | withdrawn | Accomack, Virginia |
| Bayview 25kV | X3-047 | Wind | 5.0 MW | withdrawn | Northampton, Virginia |
| Tasley | V4-022 | Solar | 5.0 MW | withdrawn | Accomack, Virginia |
| Bayview 25kV | Y2-109 | Gas | 0.5 MW | operational | Northampton, Virginia |
| Tasley - Oak Hall 69 kV II | AG2-629 | Battery | 0.0 MW | withdrawn | Accomack, Virginia |
Recent material changes
No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Track queue activity connecting through ODEC.
Start tracking with interXdata