ODEC — Interconnection Queue Projects

ODEC is associated with 32 tracked interconnection projects representing 740 MW of requested capacity.

Entity resolution: single source organization name; no cluster merge applied.

32Projects
0Active
4Operational
28Withdrawn
740 MWRequested capacity
0Markets

Capacity by technology

TechnologyProjectsRequested capacity
Solar20478 MW
Wind4168 MW
Battery565 MW
Gas329 MW

Geographic footprint

StateProjects
Virginia30
Maryland2

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Oak Hall 138kVW3-054AWind95.0 MWwithdrawnAccomack, Virginia
Belle Haven-Tasley 69 kVAE1-192Solar70.0 MWwithdrawnAccomack, Virginia
Tasley - Oak Hall 69 kVAG1-429Solar58.7 MWwithdrawnAccomack, Virginia
Tasley-Kellam 69kVY1-008Wind50.0 MWwithdrawnAccomack, Virginia
Plaintation Creek 69 kVAF2-055Solar45.0 MWwithdrawnNorthampton, Virginia
Tasley-Oak Hall 69kV IIAB2-192Solar20.0 MWwithdrawnAccomack, Virginia
Oak Hall-Hallwood 69 kVAG2-103Solar20.0 MWwithdrawnAccomack, Virginia
Tasley-Kellam 69kVV4-064Solar20.0 MWwithdrawnAccomack, Virginia
Tasley-Oak Hall 69kV IAB2-165Solar20.0 MWwithdrawnAccomack, Virginia
Tasley-Kellam 69kVW1-009Solar20.0 MWwithdrawnAccomack, Virginia
Tasley 69kVAH2-050Battery20.0 MWwithdrawnAccomack, Virginia
Bayview 69kVAH2-048Battery20.0 MWwithdrawnNorthampton, Virginia
Tasley-Kellam 69kVW1-008Solar20.0 MWwithdrawnAccomack, Virginia
Kellam - Bayview 69kVX4-014Battery20.0 MWwithdrawnNorthampton, Virginia
Weirwood-Eastville 69kVZ2-012Solar20.0 MWoperationalNorthampton, Virginia
BayviewV2-045Solar20.0 MWwithdrawnNorthampton, Virginia
Wallops Island 69 kVAE1-145Solar20.0 MWwithdrawnAccomack, Virginia
Wattsville-Wallops Island 69kVAB2-164Solar20.0 MWwithdrawnAccomack, Virginia
Greenbush 69kVAH1-169Solar20.0 MWwithdrawnAccomack, Virginia
Oak Hall-Perdue 69 kVAG2-102Solar20.0 MWwithdrawnAccomack, Virginia
Rock SpringsR20Gas20.0 MWoperationalCecil, Maryland
BayviewV3-061Solar20.0 MWwithdrawnNorthampton, Virginia
Tasley 69kVAC1-009Solar20.0 MWwithdrawnAccomack, Virginia
Weirwood-Eastville 69kVX3-040Wind18.0 MWwithdrawnNorthampton, Virginia
Tasley 69kVAB2-033Solar10.0 MWwithdrawnAccomack, Virginia
Tasley 69kVAC1-052Solar9.0 MWwithdrawnAccomack, Virginia
Rock Springs 500kVU4-015Gas8.7 MWoperationalCecil, Maryland
Tasley 25 kVAF1-243Battery5.0 MWwithdrawnAccomack, Virginia
Bayview 25kVX3-047Wind5.0 MWwithdrawnNorthampton, Virginia
TasleyV4-022Solar5.0 MWwithdrawnAccomack, Virginia
Bayview 25kVY2-109Gas0.5 MWoperationalNorthampton, Virginia
Tasley - Oak Hall 69 kV IIAG2-629Battery0.0 MWwithdrawnAccomack, Virginia

Recent material changes

No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Track queue activity connecting through ODEC.