Crane County, Texas — Interconnection Projects
The interXdata warehouse tracks 24 interconnection projects in Crane, Texas, representing 5,049 MW of requested capacity.
24Total projects
1Active
19Operational
3Withdrawn
5,049 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 11 | 2,569 MW |
| Other | 10 | 1,927 MW |
| Battery | 3 | 553 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Point Mountain Solar | 22INR0236 | Solar | 514.0 MW | withdrawn | Crane, Texas |
| Western Flats Storage | 26INR0188 | Other | 410.7 MW | operational | Crane, Texas |
| Western Flats Solar | 26INR0110 | Solar | 410.2 MW | operational | Crane, Texas |
| Cattle Drive Solar | 29INR0013 | Solar | 307.0 MW | operational | Crane, Texas |
| Tierra Loma Solar | 29INR0279 | Solar | 250.0 MW | operational | Crane, Texas |
| Soda Lake BESS 2 SLF | 24INR0383 | Other | 205.3 MW | operational | Crane, Texas |
| Tri-X BESS 1 SLF | 28INR0389 | Other | 205.3 MW | operational | Crane, Texas |
| Soda Lake BESS 1 | 23INR0501 | Other | 203.9 MW | operational | Crane, Texas |
| Crossett Power Management LLC | 66009_BA | Battery | 203.0 MW | operational | Crane, Texas |
| Crossett Power Batt | 21INR0510 | Other | 203.0 MW | operational | Crane, Texas |
| Soda Lake Solar 1 | 18INR0040 | Solar | 202.6 MW | withdrawn | Crane, Texas |
| Soda Lake Solar 2 SLF | 23INR0080 | Solar | 201.7 MW | operational | Crane, Texas |
| Tri-X Solar 1 SLF | 20INR0143 | Solar | 201.5 MW | operational | Crane, Texas |
| BRP Pictor BESS | 22INR0385 | Other | 201.1 MW | operational | Crane, Texas |
| Tierra Loma Storage | 29INR0280 | Other | 200.0 MW | operational | Crane, Texas |
| Mendoza Trail BESS | 68581_MTB | Battery | 200.0 MW | active | Crane, Texas |
| Tri-County Solar | 19INR0017 | Solar | 177.8 MW | suspended | Crane, Texas |
| Fowler Ranch | 18INR0039 | Solar | 152.5 MW | operational | Crane, Texas |
| TIMBERWOLF BESS 2 | 22INR0495 | Other | 150.0 MW | operational | Crane, Texas |
| Crane Solar Project | 63519_CRN1 | Solar | 150.0 MW | operational | Crane, Texas |
| Revolution | 66170_1 | Battery | 150.0 MW | operational | Crane, Texas |
| BRP Ampato BESS | 23INR0074 | Other | 121.6 MW | operational | Crane, Texas |
| Fowler Ranch Storage | 23INR0308 | Other | 26.1 MW | operational | Crane, Texas |
| SHIELD Solar | 20INR0279 | Solar | 1.9 MW | withdrawn | Crane, Texas |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Crane II Solar Electric, LLC | 4 | 814 MW |
| Hecate Energy | 3 | 1,335 MW |
| Tierra Loma Solar, LLC | 2 | 450 MW |
| Crane BESS, LLC | 2 | 176 MW |
| Mendoza Trail BESS, LLC | 1 | 204 MW |
| MERIT SI DEVELOPMENT, LLC | 1 | 2 MW |
| Crossett Power Management LLC | 1 | 203 MW |
| CED Crane Solar 2, LLC | 1 | 152 MW |
| BRP Pictor BESS LLC | 1 | 201 MW |
| BRP Ampato BESS LLC | 1 | 122 MW |
| Arrington Solar | 1 | 203 MW |
| Cattle Drive Solar, LLC | 1 | 307 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Crane County.