Val Verde County, Texas — Interconnection Projects
The interXdata warehouse tracks 23 interconnection projects in Val Verde, Texas, representing 3,558 MW of requested capacity.
23Total projects
5Active
13Operational
3Withdrawn
3,558 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 5 | 1,593 MW |
| Wind | 4 | 1,201 MW |
| Battery | 7 | 584 MW |
| Other | 4 | 179 MW |
| Gas | 3 | 1 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Pumpville Ranch 1 | 25INR0398 | Solar | 1,000.0 MW | suspended | Val Verde, Texas |
| Green Valley Wind | 18INR0057 | Wind | 500.0 MW | withdrawn | Val Verde, Texas |
| Lone Bow Solar | 26INR0419 | Solar | 277.5 MW | active | Val Verde, Texas |
| Blue Hills Wind Project | 67542_BHWP | Wind | 276.0 MW | active | Val Verde, Texas |
| Blue Hills Wind | 20INR0271 | Wind | 276.0 MW | suspended | Val Verde, Texas |
| Rocksprings | 60217_RKSP | Wind | 149.3 MW | operational | Val Verde, Texas |
| Blue Valley Solar | 23INR0352 | Solar | 148.0 MW | withdrawn | Val Verde, Texas |
| Zodiac Storage | 27INR0397 | Battery | 125.6 MW | active | Val Verde, Texas |
| Evans Creek Energy Storage Project | 68334_EVCRK | Battery | 103.0 MW | active | Val Verde, Texas |
| Evans Creek Energy Storage | 26INR0260 | Other | 103.0 MW | operational | Val Verde, Texas |
| Tierra Seca BESS | 23INR0364 | Battery | 102.7 MW | active | Val Verde, Texas |
| Tierra Seca | 68748_TS | Battery | 100.0 MW | operational | Val Verde, Texas |
| VISOL 1 SOLAR | 25INR0546 | Solar | 94.8 MW | operational | Val Verde, Texas |
| Antlia BESS | 22INR0349 | Battery | 72.4 MW | operational | Val Verde, Texas |
| Blue Star Solar | 24INR0146 | Solar | 72.3 MW | withdrawn | Val Verde, Texas |
| Antlia | 65588_ANTLA | Battery | 70.0 MW | operational | Val Verde, Texas |
| Amistad Dam & Power | 6128_1 | Other | 33.0 MW | operational | Val Verde, Texas |
| Amistad Dam & Power | 6128_2 | Other | 33.0 MW | operational | Val Verde, Texas |
| Hamilton BESS | 23INR0554 | Other | 9.9 MW | operational | Val Verde, Texas |
| Hamilton BESS | 66782_HAMIL | Battery | 9.9 MW | operational | Val Verde, Texas |
| WAL447 | 64775_GEN2 | Gas | 0.4 MW | operational | Val Verde, Texas |
| WAL447 | 64775_GEN1 | Gas | 0.4 MW | operational | Val Verde, Texas |
| WAL447 | 64775_GEN3 | Gas | 0.4 MW | operational | Val Verde, Texas |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| GH America Energy, LLC | 1 | 72 MW |
| Eon | 1 | 500 MW |
| Tierra Seca BESS, LLC | 1 | 103 MW |
| Greenalia Solar Power Lone Bow LLC | 1 | 277 MW |
| VISOL 1 SOLAR, LLC | 1 | 95 MW |
| BRP Antlia BESS LLC | 1 | 72 MW |
| Evans Creek Energy Storage LLC | 1 | 103 MW |
| Blue Valley Solar, LLC | 1 | 148 MW |
| Grenergy USA | 1 | 126 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Val Verde County.